4 typists are employed to complete a work in 12 days. If two more typists are added, they will finish the same work in _______ days.
A
10
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
9
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
8
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
7
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is C 8 Let they will take 𝑥 more days to finish the work.
As the number of typist increases, then the number of days to complete work decreases.
In the case of inverse proportion we take, x1×y1=x2×y2
Here, x1=4;y1=12;x2=4+2=6 and y2=x ∴4×12=6×x ⇒x=4×126=8 ⇒x=8
∴ They will finish the same work in 8 days.