40 construction workers were building a house. Each day, they were able to build 160 of the house. How many more workers should be hired if the owner of the house wants the house to be completed in 30 days?

A
40
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
80
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
60
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
20
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is A 40
If more workers are hired, the house can be completed in less number of days.
This is a case of inverse proportion.

Let the number of days taken by 40 workers to finish the house be x.
The workers can construct 160 of the house in a day.
Based on this infromation, we can write:
160× x = 1
x = 60
40 workers need 60 days to construct the house.
Using the formula for inverse proportion,
Number of workers× Number of days = constant
40 × 60 = 30 × Number of workers required
Number of workers required = 40 × 6030=80
80 workers can finish the work in 30 days.
8040=40 more workers are required to build the house in 30 days.

flag
Suggest Corrections
thumbs-up
1
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Inverse Proportion
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon