40 men can do a piece of work in a given times If only 30 men be changed, 6 more days needed t complete the work. In how many days can 60 men do the work ?
A
9
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
10
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
12
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
15
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is D 12 Suppose 40 men can do a piece of work in x days Then 30 men can do the same work in x×4030 days = (x + 6) days ⇒ 4x = 3x + 18 ⇒ x = 18 ∴ 60 men can do the same work in 18×4060 days = 12 days