45 men working 8 hours a day can finish a project within a given time. Five men are unable to report for the work. How long should the rest work a day to finish the project on time.
A
10hrs
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
12hrs
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
9hrs
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
8hrs
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is C9hrs
Total Work Hours are
⇒45×8
When 5 Do not Report ,then Only 45−5=40 men will remain
So Now, Let us Assume the No of Hours beH they now have to work to finish the project