Question
50 men mow 32 hectares of land in 3days . How many days will 15men take to mow it.
Open in App
Solution
Land is same (32 hectares) in both cases.
50 men can mow land in =
3 days.
.˙. 1 man will mow it in = (3 x 50) days.
then, 15 men men will mow it in = (3x50)÷15 = 150÷15 = 10
Answer =
10 days.
Suggest Corrections
24
Similar questions
Q.
A can mow a field in
9
days; B can mow it in
12
days while C can mow it in
8
days. They all together mowed the field and received Rs.
1610
for it. How will the money be shared by them?
Q.
A
and
B
working together can mow a field in
56
days and with the help of
C
, they could have mowed it in
42
days. How long would
C
take by himself ?
Q.
If
15
men complete a task in
3
days, how many days will
9
men take to complete it?
Q.
It takes
1.5
hours for Tim to mow the lawn. Linda can mow the same lawn in
2
hours. How long will it take John and Linda, work together, to mow the lawn?
Q.
Mohan takes 9 hours to mow a large lawn. He and Sohan together can mow it in 4 hours. How long will Sohan take to mow the lawn if he works alone?
View More
Join BYJU'S Learning Program
Grade/Exam
1st Grade
2nd Grade
3rd Grade
4th Grade
5th Grade
6th grade
7th grade
8th Grade
9th Grade
10th Grade
11th Grade
12th Grade
Submit
Related Videos
Time and Work
MATHEMATICS
Watch in App
Explore more
Time and Work
Standard VII Mathematics
Join BYJU'S Learning Program
Grade/Exam
1st Grade
2nd Grade
3rd Grade
4th Grade
5th Grade
6th grade
7th grade
8th Grade
9th Grade
10th Grade
11th Grade
12th Grade
Submit
AI Tutor
Textbooks
Question Papers
Install app