CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

8 men and 10 boys do a work in the same days as 4 men and 16 boys do. 1 man and 3 boys start a work to finish it in 40 days. After eighteen days, 920 th part of work had been finished. How many boys should be increased to make the work complete in exact time ?

Open in App
Solution

According to given condition,
8M+10B=4M+16B
4M=6B
2M=3B
M=3 units/day
B=2 units/day
In second condition, it is given that,
1 man and 3 boys complete the same work in 40 days
After eighteen days,
1 man and 3boys complete920 th part of work
i.e. (1×3+3×2)×18=162 units of work in 18 days
162=920×total work
total work = 360 units
So. remaining work = 360162=198units
let x no. of boys are added to complete the work in 22 remaining days
198 units of work in 22 days =22×(1×3+[3+x]×2)
198=22×(3+6+2x)
9=3+6+2x
x=0
Hence no additional boys are required.

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Time and Work
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon