8 men working for 9 hours a day can complete a piece of work in 20 days. In how many days can 7 men working for 10 hours a day complete the same piece of work?
A
2012days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
2035days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
21 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
2047days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution
The correct option is C2047days 8 men working for 9 hours a day can complete a piece of work in 20 days 8 men working for 1 hour a day can complete the work in (20 x 9) days (Less hours, More days) 1 man working for 1 hour a day can complete the work in (20 x 9 x 8) days (Less men, more days)
1 man working for 10 hours a day can complete the work in (20×9×810) days
7 men working for 10 hours a day can complete the work in (20×9×87×10) days = 1447 days = 2047 days