Question
800 men can finish a given work in 6 days. How many more men are needed to finish the same work in 40 days?
Open in App
Solution
Hi
,
using
the
man
×
days
=
constant
method
,
M
1
×
D
1
=
M
2
×
D
2
800
×
6
=
M
2
×
40
M
2
=
4800
40
=
120
men
So
120
mens
are
required
.
Regards
Suggest Corrections
0
Similar questions
Q.
40 men can finish a piece of work in 26 days. How many men will be needed to finish it in 16 days?
Q.
If 5 men can finish a work in 12 days, then how many men will be required to finish the same work in 5 days?
Q.
If 6 men and 2 women can finish the work in 12 days.Then in how many days 9 men and 3 women can finish the work?
Q.
40 men can do a piece of work in a given times If only 30 men be changed, 6 more days needed t complete the work. In how many days can 60 men do the work ?
Q.
9 men can finish a task in 4 days. How many days will 6 men take to finish the same task ?
View More
Join BYJU'S Learning Program
Grade/Exam
1st Grade
2nd Grade
3rd Grade
4th Grade
5th Grade
6th grade
7th grade
8th Grade
9th Grade
10th Grade
11th Grade
12th Grade
Submit
Related Videos
Inverse Variation
MATHEMATICS
Watch in App
Explore more
Inverse Proportion
Standard VII Mathematics
Join BYJU'S Learning Program
Grade/Exam
1st Grade
2nd Grade
3rd Grade
4th Grade
5th Grade
6th grade
7th grade
8th Grade
9th Grade
10th Grade
11th Grade
12th Grade
Submit
AI Tutor
Textbooks
Question Papers
Install app