Q. In Snyder's method of synthetic unit hydrograph development, basin lag is taken as
- the time interval between centroid of the rainfall excess and surface runoff
- the time interval from mid point of the unit rainfall excess to the peak of the unit hydrograph
- independent of rainfall duration
- independent of catchment characteristics
Q. In constructing a 4 hour synthetic unit hydrograph for a basin, the lag time is estimated to be 40 hours. When will the peak discharge in the Synthetic Unit Hydrograph occur from the start of the storm?
- 36 hours
- 40 hours
- 42 hours
- 44 hours
Q. The peak discharge, by using Snyder's method of unit hydrograph of standard duration (hour)having catchment area, regional constant and basin lag as 200 km2, 0.6 and 6 hour respectively, will be
- 51.28m3/sec
- 55.6m3/sec
- 60.75m3/sec