Slip Loss and Relaxation of Steel
Trending Questions
Q.
What is capillary action in soldering?
Q. The percentage loss of prestress due to anchorage slip of 3 mm in a concrete beam of length 30 m which is post-tensioned by a tendon with an initial stress of 1200 N/mm2 and modulus of elasticity equal to 2.1×105 N/mm2, is
- 0.0175
- 0.175
- 1.75
- 17.5
Q. In case of Magnet-Blaton system of prestressing, each sandwich can generally anchor
- 6 wires
- 8 wires
- 10 wires
- 16 wires
Q. the magnitude of loss of prestress due to relaxation of steel is in the range of
- zero to 1%
- 2 to 8%
- 8 to 12%
- 12 to 14%
Q. Spalling stresses are produced in post-tensioned pre-stressed concrete members at
- locations of maximum bending moment only
- locations of maximum shear zone
- anchorage zone
- bond-developing zone
Q. In case of prestressed concrete members, the bursting stresses develops at
- Bond zone
- Maximum bending moment zone
- Maximum shear stress zone
- Anchorage zone
Q. At the time of initial tensioning, the maximum tensile stress immediately behind the anchorage should not exceed which one of the following?
- 0.50 ×ultimate tensile stress
- 0.60 ×ultimate tensile stress
- 0.70 ×ultimate tensile stress
- 0.80 ×ultimate tensile stress
Q. The loss due to relaxation of stress in steel in PSC member depends on
- Applied stress level
- Temperature
- Type of steel
- 1 and 2 only
- 2 and 3 only
- 1, 2 and 3
- 1 and 3 only
Q. A simply supported prestressed concrete beam is of 25 m span. The initial stress is 1000 MPa.
The slip in the jack during tensioning has been 2 mm, If Es=200 GPa, the loss prestress due to anchorage slip is
The slip in the jack during tensioning has been 2 mm, If Es=200 GPa, the loss prestress due to anchorage slip is
- 16%
- 12%
- 10%
- 1.6%
Q. Spalling stresses are produced in post-tensioned pre-stressed concrete members because of
- bursting force
- highly concentrated tendon force
- inadequate anchor block
- maximum shear zone
Q. The percentage loss of pre-stress due to anchorage slip of 3 mm in a concrete beam of length 30 m, which is post-tensioned by a tendon with an initial stress of 1200 N/mm2 and modulus of elasticity equal to 2.1 x 105N/mm2 is
- 0.0175
- 0.175
- 1.75
- 17.5
Q. Match List -I (Post - tensioning system) with List - II (Type of anchorage) and select the correct answer using the codes given below the lists:
List- I
A. Freyssient
B. Gifford-Udall
C. Lee-McCall
D. Magnel Blaton
List- II
1. Flat steel wedges in sandwich plates
2. High strength nuts
3. Split conical wedges
4. Conical serrated concrete wedges
Codes:
A B C D
List- I
A. Freyssient
B. Gifford-Udall
C. Lee-McCall
D. Magnel Blaton
List- II
1. Flat steel wedges in sandwich plates
2. High strength nuts
3. Split conical wedges
4. Conical serrated concrete wedges
Codes:
A B C D
- 2 1 4 3
- 4 3 2 1
- 2 3 4 1
- 4 1 2 3