A 5-stage pipeline processor executes 100 instruction and takes 144 cycles for execution because of sonic hazards in pipeline. A new solution is implemented to reduce the hazard's impact by 60%. How many extra cycles the new pipeline takes as compared to the pipeline execution without hazards?

Open in App
Solution

option (b)

Pipeline cycles without hazards
= (k + n -1).
k = number of stages
n = number of instructions
= 5 + 100 - 1
= 104
Pipeline cycles with hazrads
= 144(given)
Extra cycles because of hazards
= 144 - 104
= 40
Extra cycles in new pipeline
= 40 * 40%
= 16


flag
Suggest Corrections
thumbs-up
0
similar_icon
Similar questions
View More
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Handling Hazards 2
OTHER
Watch in App
Join BYJU'S Learning Program
CrossIcon