A 50 Hz generator is delivering 60% of power that it is capable of delivering through a transmission line to an infinite bus. A fault occurs that increases the reactance between the generator and the infinite bus to 400% of the value before the fault. When fault is isolated, the maximum power that can be delivered is 75% of the original maximum value. For this condition critical clearing angle (in degres) is