A alone can do a piece of work in 15 days to that of B alone can do it in 10 days. If B works at it for 5 days and then leaves, then A alone can finish the remaining work in _________.
A
612days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
712days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
8days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
6days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is A712days A can do a work in 15 days