A alone can finish a piece of work in 10 days which B alone can do in 15 days. If they work together and finish it, then out of total wages of t 3000. A will get
(a) Rs 1200
(b) Rs 1500
(c) Rs 1800
(d) Rs 2000
Total wages =Rs 3000
A's 1 day's work =110
B's 1 day's work =115
∴ Ratio in thier work =110:115
=3:230=3:2
∴ A's share =Rs.3000×33+2
=Rs.3000×35=Rs.1800