A and B can complete a task in 12 days. However, A had to leave a few days before the task was complete and hence it took 16 days in all to complete task. If A alone could complete the work in 21 days, how many days before the work getting over did A leave?

A
7
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
9
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
5
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
0
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is A 7

B can alone do the work
=1112121 days

1B=7484=384=128

=28 Days

Let A worked X days, So

Work done by A+ Work done by B=1

X21+1628=1

X21=1228

X=9

Hence, A worked for 9 days means A left work before (169)=7 days of completion.


flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Multiplication of Integers
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon