A and B can do a given work in 8 days,B and C can do the same work in 12 days , and A,B,C complete it in 6 days. In how many days can A and C will finish the same work?
Open in App
Solution
A+B 1 day work = 1/8 B+C 1 day work = 1/12 A+B+C 1 day work = 1/6
We can get A work by (A+B+C)-(B+C) And C by (A+B+C)-(A+B)