wiz-icon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

A and B can do a piece of work in 30 days. While B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days before B and C leave. How many days more will A take to finish the work?

A
18 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
24 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
30 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
36 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is B 18 days
(A+B)'s one day's work =130

(B+C)'s one day's work =124..........(1)

(C+A)'s one day's work =120

(A+B+C)'s one day's work =12[130+124+120]=12×[20+25+30600]=751200=116...........(2)

(A+B+C)'s 10 day's work =1016=58

Remaining work, 158=38 (which is done by A)

From (1) and (2), A's one day's work =116124=148

Remaining 38 of the work is done by A alone in 38×48=18 days.

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Time and Work
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon