A and B can do a piece of work in 30 days. While B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days before B and C leave. How many days more will A take to finish the work?
A
18 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
24 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
30 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
36 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is B 18 days (A+B)'s one day's work =130
(B+C)'s one day's work =124..........(1)
(C+A)'s one day's work =120
∴(A+B+C)'s one day's work =12[130+124+120]=12×[20+25+30600]=751200=116...........(2)
(A+B+C)'s 10 day's work =1016=58
Remaining work, 1−58=38 (which is done by A)
From (1) and (2), A's one day's work =116−124=148
∴ Remaining 38 of the work is done by A alone in 38×48=18 days.