CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

A and B can do a piece of work in 40 days, B and C in 30 days, and C and A in 24 days. How long does it take if they work on it together?

A
14 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
30 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
20 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
18 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is C 20 days
Given A and B do work in 40 days.and Band C do work in 30 days and C and A do work in 24 days
Then, A and B one day work =140
B and C one day work =130
C and A one day work =124
Summing up the above three equations give,
2( A+B+C) one day work =140+130+124=60600=110
So A+B+C one day work =120
A, B and C can do the work together in 20 days

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Introduction to Direct Proportions
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon