CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

A and B can do a piece of work in 6 days and 4 days respectively. A started the work; worked at it for 2 days and then was joined by B. Find the total time taken to complete the work.

Open in App
Solution

As 1 day work

Bs 1 day work =14

A and day work =16+14=16

=2+312=512

As 2 day work =16×2=13

Remaining work =113=23 [ whole work =1]

Now A and B can do 512th work in 1 day

They will do 1 work (Whole work) in 1×125 daysBs

and they will do 23th1 work =125×23

=85=135 days

Total work was finished in =135+2

=335 days [abc+d=(a+d)bc]


flag
Suggest Corrections
thumbs-up
286
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Inverse Proportions
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon