Question

A and B can do a piece of work in 8 days. B and C can do the same work in 12 days. If A,B and C can complete the same work in 6 days, in how many days can A and C complete the same work?

A
8 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
10 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
6 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
2 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is A 8 days
(A+B+C)'s one days' work =16;(A+B)'s one days' work =18;
(B+C)'s one days' work =112
C's one days' work =1618=4324=124
Similarly, A's one days' work =16112=2112=112
(A+C)'s one days' work =124+112=1+224=324=18
(A+C) can finish the work in 8 days.

flag
Suggest Corrections
thumbs-up
1
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Division of Algebraic Expressions
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon