A and B can do a work in 10 days. B and C can do the same work in 15 days. C and A can complete the same work in 20 days. In how many days can C alone complete the work ?

A
120 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
118 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
115 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
110 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is A 120 days
In 10 days A and B does 1 work.
In 1 day A and B will do 110 work -(i)
In 15 days B and C does 1 work
In 1 day B and C will do 115 work -(ii)
In 20 days C and A does 1 work
In 1 day C and A will do 120 work - (iii)
Adding equation(i),(ii)and (iii)
In1 day 2(A+B+C) will do(110+115+120)
In1 day 2(A+B+C) will do 1360
work.
In 1 day (A+B+C) will do13120 work
In 1 d a y(A+B)+(C) will do13120 work
A+B does 110 work in 1 day
work done by C in 1 day
=13120110
=1120
1120 work is done by C in 1 day.
1 work is done by C in 120 days.
Answer: option (A)

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Time and Work
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon