A and B can do a work in 40 days, B and C in 10 days, C and A in 8 days. If A, B and C work together, they will complete the work in?
8 days
(A + B)'s 1 days work =140; (B + C)'s 1 days work =110; (A + C)'s 1 day's work =18
Adding, we get : 2 (A + B + C)'s 1 day's work =(140+110+18)=1040=14
∴ (A + B + C)'s 1 days work =18
So, A, B and C together can complete the work in 8 days.