Question

A and B can do a work in 8 days, B and C can do the same work in 12 days. A,B and C together can finish it in 6 days. A and C together will do it in:

A
4 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
6 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
8 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
12 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is C 8 days
(A+B+C)'s 1 day's work =16;
(A+B)'s 1 day's work =18;
(B+C)'s 1 day's work =112;
(A+C)'s 1 day's work =(2×16)(18+112)
=(13524)=324=18.
So, A and C together will do the work in 8 days.

flag
Suggest Corrections
thumbs-up
4
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Time and Work
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon