wiz-icon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

A and B can do a work in 8 days , B and C in 12 days, and A and C in 16 days. In how many days can they complete the work, all working together ?

A
4217
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
7513
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
696
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
4813
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Join BYJU'S Learning Program
CrossIcon