Question

A and B can do a work in 8 days. B and C together in 6 days while C and A together in 10 days. If they all work together, in The work will be completed in k17 days, where k is

Open in App
Solution

Given that:

(A+B)s one day work=18 ......(1)

(B+C)s one day work=16 ......(2)

(A+C)s one day work=110 ......(3)

On adding all the above equations, we get
2(A+B+C)s one day work=18+16+110,

2(A+B+C)s one day work=15+20+12120,

(A+B+C)s one day work=472×120,

(A+B+C)s one day work=47240.

Hence, A,B,C will complete the work together in 24047 days.