Question

A and B can do a working days B and C can do the same work in 12 days. A, B and C together can finish it in 6 days. A and C will do it in -

A
4 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
6 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
8 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
12 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is C 8 days
1A+1B=18 ....(i)
1B+1C=112 ...(ii)
1A+1B+1C=116 ...(iii)
(iii) - (i)
1C=1618=4324124
(iii) - (ii)
1A=16112=2112=112
1A+1C=124+112=1+224=324=18
So A, C do in 8 days

flag
Suggest Corrections
thumbs-up
1
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Time and Work
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon