CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

A and B can independently finish a piece fo work in 36 and 45 days respectively. They started working together and after a few days A left. After that B could finish the remaining work in 36 days. After how many days of working together did A leave?

Open in App
Solution

A's one day work =136
B's one day work =145
(A+B)'s one day work =136+145=5+4180=9180
Work done by B in 36day=3645
Remaining work =13645=945
Number of days A worked =945÷9180=945×1809=4

flag
Suggest Corrections
thumbs-up
7
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Unitary Method
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon