A and B can independently finish a piece of work in 36 and 45 days respectively. They started working together and after a few days A left. After that B could finish the remaining work in 36 days. After how many days of working together did A leave?

A
8 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
4 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
12 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
6 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is B 4 days
A's one day work =136
B's one day work =145
(A+B)'s one day work =136+145=5+4180=9180
Work done by B in 36day=3645
Remaining work =13645=945
Number of days A worked =945÷9180=945×1809=4

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Time and Work
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon