CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

A and B can together finish a work in 30 days. They worked together for 20 days and then B left. After another 20 days, A finished the remaining work. In how many days A alone can finish the job?


A

40

No worries! We‘ve got your back. Try BYJU‘S free classes today!
B

54

No worries! We‘ve got your back. Try BYJU‘S free classes today!
C

60

Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D

59

No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is C. 60

Total time taken by A and B to finish a units of work =30 days

Therefore work done by A and B in 1 day =130 units of total work

Now, total work done in 20 days =130×20=23 units of work

Hence, amount of work left =123=13 units of work

This work was completed by A alone in 20 days.

Therefore, days taken by A to complete a unit of work =20÷13=60 days

Hence, it would take 60 days for A to complete the whole work.


flag
Suggest Corrections
thumbs-up
245
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Introduction to Inverse Proportions
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon