A and B can together finish a work in 30 days. They worked together for 20 days and then B left. After another 20 days, A finished the remaining work. In how many days A alone can finish the job?
The correct option is C. 60
Total time taken by A and B to finish a units of work =30 days
Therefore work done by A and B in 1 day =130 units of total work
Now, total work done in 20 days =130×20=23 units of work
Hence, amount of work left =1−23=13 units of work
This work was completed by A alone in 20 days.
Therefore, days taken by A to complete a unit of work =20÷13=60 days
Hence, it would take 60 days for A to complete the whole work.