wiz-icon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

A and B complete a piece of work in 24 days. B and C do the same work in 36 days; and A, B and C together finish it in 18 days. In how many days will

i) A alone,

ii) C alone,

iii) A and C together, complete the work?

Open in App
Solution

A and B complete a piece of work in = 24 days
B and C complete a piece of work in = 36 days
(A+B+C) complete a piece of work in = 18 days
(A+B)'s 1 day work =124
(B+C)'s 1 day work =136
(A+B+C)'s 1 day work =118
i) A's 1 day work =118136
=2136=136
A will complete the work in = 36 days.

ii) C's 1 day work =118124
=4372=172
C will complete the work in = 72 days.

iii) (A+C)'s 1 day work =136+172
=2+172=372
=124
(A+C) will complete the work in = 24 days.


flag
Suggest Corrections
thumbs-up
14
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Inverse Proportions
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon