A and B together can complete a piece of work in 4 days. If A alone can complete the same work in 12 days, in how many days can B alone complete that work?
6 days
(A+B)’s 1 day’s work = 14
A’s 1 day’s work = 112
B’s 1 day’s work = 14−112=16
Hence, B alone can complete the work in 6 days.