A and B together can complete a work in 12 days A alone can complete it in 20 days If B now does the work for half a day dally Then in how many days A and B together will complete the work?
A
15 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
20 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
45 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
30 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is B 15 days B's 1 day's work =112−120=260=130 (A + B)'s 1 day's work =120+160=460=115.[B works for half day only] So, A and B together will complete the work in 15 days.