A and B together can complete a work in 3 days. They start together but, after 2 days, B left the work. If the work is completed after 2 more days, B alone could do the work in
A
4 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
6 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
8 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
10 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is A6 days Let the total unit of work be 6 units (LCM of 2 and 3) (A+B)do=63=2units/day (A+B)′s2day work =2×2=4units Work left =6−4=2units This remaining work is done by A in 2 days. ∴A′s per day work =22=1unit/day ∴B′s per unit work =(A+B)′swork−A′swork =2−1=1unit/day B alone can complete the work in =61=6days.