CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

A and B together can complete a work in 3 days. They start together but after 2 days, B left the work. If the work is completed after two more days, then B alone could do the whole work in

A
8 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
3 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
2 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
6 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution

The correct option is D 6 days
Let A and B alone complete the whole work in x and y days respectively.
Then, one day work of A=1x
and one day work of B=1y
According to question,
3x+3y=1
and 4x+2y=1
Solving the above two equations, we get
x=6 and y=6
So, B alone can complete the whole work in 6 days.

flag
Suggest Corrections
thumbs-up
4
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Inverse Proportions
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon