The correct option is D 60 days
Let the total work be 60 units. [LCM of 30 and 20]
A and B do 6030=2 units/day
As they worked for 20 days, they did 20×2=40 units of work.
Work left is 60−40=20 units
Thus, 20 units is finished by A in 20 days.
Hence, A does 2020=1 unit/day.
So, A alone can finish the work in 601=60 days.