A and B undertake to do a piece of work for Rs. 200. A alone can do it in 6 days and B in 8 days. With the help of C they finish it in 3 days.The amount of money paid to C is = Rs.
All the three are doing work for three days and the payment for this work is Rs. 200
A's 1 day work = 16
A’s work for 3 days = 3×16=12
∴ A gets 12×Rs.200=Rs.100
B's 1 day work = 18
B’s work for 3 days 3×18=38
∴ B gets 38×Rs.200=Rs.75
∴ C gets the rest, i.e., (Rs. 200 - Rs. 100 - Rs. 75) = Rs.25