A and B undertake to do a piece of work for Rs.600. A alone can do it in 6 days while B alone can do it in 8 days. With the help of C they finish it in 3 days. Find B's share.
Open in App
Solution
Comparing Work per day, we get
⇒W6+W8+WC=W3
⇒16+18+1C=13
⇒C=24
Now, Salary is to be divided according to the Proportion of Work