A and B. working together can finish a piece of work in 6 days, while A alone can do it in 9 days. How much lime will B alone take to finish it?
Given,
A and B both's one day's work =16
A's alone's one day's work =19
∴ B's alone one day's work \\=16−19
=3−218=118
∴ B can finish the work in 18 days