A and B working together can mow a field in 56 days and with the help of C , they could have mowed it in 42 days. How long would C take by himself ?
A
168 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
180 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
151 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
140 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is A168 days A+B's 1 day work =156 A+B+C 's 1 day work =142 Thus, C's 1 day work =142−156 =4−3168=1168 Hence, C can complete work in 168 days.