A, B and C can alone complete a work in 10, 12 and 15 days respectively. A and C started the work and after working for 4 days, A left and B joined. In how many days the total work was completed?
A
659days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
629days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
6days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
549days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
E
729days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is B629days (A+C)=110+115=16. They worked for 4 days so did 16×4=23=23rd of work Remaining work =1−23=13 Now A left, B and C working (B+C)=(112+115)=960=320. They worked for x days and completed 13rd of work so 320×x=13, so x=209days Total =4+209