Question

A, B and C can alone complete a work in 10, 12 and 15 days respectively. A and C started the work and after working for 4 days, A left and B joined. In how many days the total work was completed?

A
659 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
629 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
6 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
549 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
E
729 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is B 629 days
(A+C)=110+115=16. They worked for 4 days so did
16×4=23=23rd of work
Remaining work =123=13
Now A left, B and C working
(B+C)=(112+115)=960=320. They worked for x
days and completed 13rd of work so 320×x=13, so x=209days
Total =4+209


flag
Suggest Corrections
thumbs-up
2
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Unitary Method
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon