A,B and C can do a piece of work in 11 days, 20 days, and 55 days respectively working alone. How soon can the work be done if A is assisted by B and C on alternate days?

A
7 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
8 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
9 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
10 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!