CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

A, B and C can do a piece of work in 11 days, 20 days and 55 days respectively, working alone. How soon can the work he done if A is assisted by B and C on alternate days?

A
7 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
8 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
9 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
10 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is B 8 days
Let the total work be 220 units (LCM of 11, 20 & 55).
A does =22011 = 20 units / day
B does = 22020 = 11 units / day
C does =22055=4 untis /day
according to the question,
(A + B) + (A + C) + (A + B) + (A + C) + .........
(20 + 11) +(20 + 4) + (20 + 11) + (20 + 4) +.
In 2 days, work get completed = 55 units.
55 units of work completed in 2 days.
220 units of work completed in
= 255×220=2×4 = 8days.

flag
Suggest Corrections
thumbs-up
1
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Time and Work
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon