A, B and C can do a piece of work in 11 days, 20 days and 55 days respectively, working alone. How soon can the work he done if A is assisted by B and C on alternate days?
A
7 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
8 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
9 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
10 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is B 8 days Let the total work be 220 units (LCM of 11, 20 & 55). A does =22011 = 20 units / day B does = 22020 = 11 units / day C does =22055=4 untis /day according to the question, (A + B) + (A + C) + (A + B) + (A + C) + ......... (20 + 11) +(20 + 4) + (20 + 11) + (20 + 4) +. In 2 days, work get completed = 55 units. 55 units of work completed in 2 days. 220 units of work completed in = 255×220=2×4 = 8days.