A, B and C can do a work together in a certain number of days. If A leaves after half the work is done, then the work takes 4 more days for completion, but if B leaves after half the work is done, the work takes 5 more days for completion. If A takes 10 more days than B to do the work alone, then in how many days can C alone do the work?
52.5
Let A alone can do the work in a days, B alone in b days and C alone in c days.
Let A, B and C together completes the work in x days.
So,1a+1b+1c=1x...........(1)
Then half of the work they will complete together in x2 days.
When A leaves, Rest half of the work is done by B and C together,
(2b+2c)=1{(x2)+4}
Using (1), 2×(1x−1a)=1{(x2)+4}
Solving we get, a =[x×{(x2)+4}]4................(2)
On similar lines b =[x×{(x2)+5}]5................(3)
Given that a=b+10 ..........................(4)
Thus we have [x×{(x2)+4}]4=[x×{(x2)+5}]5+10
Solving we get x = 20.
From (2) and (3) we get
a = 70 and b = 60
Put these values in (1) we get c = 52.5 days.
Hence, choice (a) is the right option