A, B, C can do a piece of work individually in 8,10 and 15 days respectively. A and B start working by A quits after working for 2 days. After this, C joins B till the completion of work. In how many days will the work be completed?
A
53/9days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
34/7days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
85/13days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
53/10days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution
The correct option is D53/10days Work done by A in 1day=18 Work done by B in 1day=110 Work done by C in 1day=115 Work done by A and B together in 1day=18+110 =5+440=940 ∴ In 2 days A and B complete 2×940=920 of work Work remaining =1−920=1120 Work done by B and C together in 1day =110+115 =3+230=530=16 Let no. of days be n. ∴n×16=1120 n=1120×6=3310days Total no. of days =(2+3310)=5310