A bicycle chain of length 1.6m and of mass 1kg is lying on a horizontal floor. The work done in lifting it with one end touching the floor and the other end 1.6m above the floor is (Take g=10 ms2):

A
10J
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
3.2J
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
8J
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
16J
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is C 8J
Consider chain to be concentrated on its center of mass.
Therefore, change in potential energy = work done by external force.
Work done=mgh2=8J

flag
Suggest Corrections
thumbs-up
1
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Conservative Forces and Potential Energy
PHYSICS
Watch in App
Join BYJU'S Learning Program
CrossIcon