A bridge has an expected life of 50 years and is designed for a flood magnitude of return period 100 years. What is the risk associated with this hydrologic design?
A
1−(0.99)50
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
(0.5)50
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
(0.99)50
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
(0.99)100
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is A1−(0.99)50 Risk = Probability of flood being exceeded at least once over a period of n years. =1−(1−1100)50=1−(0.99)50