A budget which is designed to remain unchanged irrespective of the activities actually attained is a __________.
A
Flexible budget
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
Cash budget
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
Fixed budget
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
None of these
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is C Fixed budget Budget can be classified as fixed budget and flexible budget.
Fixed Budget is that budget which does not changes with the level of sales/production or due to increase or decrease with the activity level. Fixed Budget is also called static budget.