Question

A can complete a piece of work in 36 days and B can complete 16.66% of the work in 3 days. If they work together, then in how many days can they finish 66.66% of the work?

A
11 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
8 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
13 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
12 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
E
None of these
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is B 8 days
A completes the work in 36 days.

B completes 16.66%, i.e., 1/6th of the work in 3 days.

So, B completes the work in = 1/6 × 3 = 18 days

Total work = L.C.M of 18 and 36 = 36

A’s 1-day work = 36/36 = 1 unit

B’s 1-day work = 36/18 = 2 units

(A + B)’s 1-day work = 36/3 = 12 units

66.66%, i.e., 2/3rd of the work = 36 × 2/3 = 24 units

Required time = 24/3 = 8 days

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Basic Concepts:Unitary Method
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon