Question

A can do 23 of a certain work in 16 days and B can do 14 of the same work in 3 days. In how many days can both finish the work, working together?

Open in App
Solution

A can do 23 work in 16 daysSo, work done byA in one day = 248=124B can do 14 work in 3 daysSo, work done by B in one day =112Work done jointly by A and B in one day =124 + 112 = 1 + 224= 324 = 18So, A and B together will take 8 days to complete the work.