Question

A can do a job in 10 days and B in 20 days. They work together but 4 days before the finish of the job B leaves. Find the total days to finish the job?

A
6
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
8
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
12
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
14
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is B 8
As A finish the job in 10 days
Work done by A in 1 day = 110
Similarly, work done by B in 1 day = 120
As B leaves 4 days before the completion of work i.e. last 4 days A worked alone.
Let the no. of days A and B worked together be x.
(110+120)×x+(110×4)=1
320x+25=1
x=4
total days to finish the job = x(when A and B worked together)+4(when A worked alone)=4+4=8

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Measurement of Significant Figures
CHEMISTRY
Watch in App
Join BYJU'S Learning Program
CrossIcon